Send message to Lytag Ltd
Ask a question
Pricing/Quote
List of suppliers/where can I buy
Sample request
I have read and agree to the terms and conditions of usage and The Building Centre's Privacy Policy. Your request will be sent and shared to the selected manufacturers you submit a request to.

Find products

Use our product finder to search for products and materials

Subscribe to our newsletter to receive news about events and exhibitions, innovation and materials on the latest building product innovations, case studies and more.
I have read and agree to the terms and conditions of usage and The Building Centre's Privacy Policy.

Lewes Cliffe flood defence, The River Ouse.Sussex

13 Oct 2011
Case study
The River Ouse is located in West and East Sussex. It rises south of Crawley, passes through Lewes and the South Downs and joins the English Channel at Newhaven, East Sussex.

Following extensive flooding of Lewes in 2000, the Sussex Ouse Flood Management Strategy was published The Strategy considered Lewes to be comprised of several areas known as flood cells. One of these flood cells in Lewes is know as the Cliffe cell.

The work included raising existing flood wall heights, building new walls and installing floodgates to a 1 in 100 year Standard of Protection (SoP).

The new wall construction is a ‘Lytag® LWA concrete base with shear key and concrete flood wall’. A significant reduction of around 25% in weight was achieved for the concrete with brickwork clad wall.

The designers of the scheme ensured that the materials and design matched those previously used in the Cliffe conservation area.